Peoplecert MSP-Practitioner Exam Syllabus Topics:

TopicDetails
Topic 1
  • Problem Solving: Develop expertise in addressing complex programme management challenges and resolving issues efficiently and effectively.
Topic 2
  • Programme Management: Develop expertise in programme management best practices, mastering principles, themes and processes to help organizations manage programmes effectively.
Topic 3
  • Governance and Control: Gain an in-depth understanding of programme governance, including setting up and maintaining governance structures, accountability mechanisms and assurance processes to deliver programme success.
Topic 4
  • Quality Management: Understand quality assurance and control processes to ensure that programme deliverables and outcomes meet or exceed defined quality standards.
Topic 5
  • Stakeholder Engagement: Learn how to effectively manage diverse stakeholders, including executives, sponsors, team members, suppliers and customers, with advanced communication and relationship-building skills.

 

NEW QUESTION # 10
Which of following best defines Outcomes?

  • A. New operational state achieved after transition of capability in live operations
  • B. Deliverable of a project
  • C. Measurable improvement resulting from outcomes perceived as advantage
  • D. Completed set of project outputs

Answer: A

Explanation:
Outcomes are defined as the new operational state achieved after the transition of capability into live operations. They represent the changes in the organization's way of working resulting from the combined effect of project outputs.
The MSP Practitioner states: "Outcomes are combined outputs or projects to bring a new operational state in organization," emphasizing that outcomes go beyond deliverables to reflect actual changes in operations and behaviours.
This distinction is critical in MSP's focus on transformational change, ensuring programmes deliver real, sustainable benefits rather than just outputs.


NEW QUESTION # 11
Where in the transformational flow would the Benefits Map normally be created?

  • A. Realizing the Benefits
  • B. Managing the Tranches
  • C. Identifying a Programme
  • D. Defining a Programme

Answer: D


NEW QUESTION # 12
One of the outcomes from the programme is 'customers buy package deals'. However, this outcome cannot be fully achieved until the end of Tranche 3 when training for the call centre staff is complete. Some senior managers think that this could be delivered more quickly, but the Call Centre Manager does not want their staff members affected by too many changes at the same time, so that they can continue to meet the needs of existing customers. The programme manager has designed the tranche structure to take this into account.
Is this tranche design an appropriate application of the 'bring pace and value' principle, and why?

  • A. No, because the BCM should be responsible for deciding when the transition to new ways of working should start
  • B. Yes, because the programme manager should be empowered to design the delivery plan to meet the business needs
  • C. No, because the priority of the programme is to deliver the vision and benefits as early as possible
  • D. Yes, because the timing of delivery must consider the needs of normal business-as-usual activities

Answer: D

Explanation:
Comprehensive and Detailed 200 to 250 words of Explanation From Exact Extract of project- programme-and-portfolio-management of 5th Edition MSP:
The principle of 'Bring pace and value' in MSP 5th Edition emphasizes that a programme should be structured to deliver value as early as possible while maintaining a sustainable pace of change. A critical aspect of this principle is the recognition of the "capacity for change" within the business-as-usual (BAU) environment. If a programme attempts to move too quickly, it risks overwhelming the operational teams, leading to a dip in performance or a complete failure to adopt the new ways of working.
In this scenario, the Call Centre Manager highlights a valid concern regarding the volume of change (change fatigue) and the need to maintain existing customer service levels. Option A is the correct application of the principle because MSP explicitly states that the design of tranches and the timing of "landing points" must be balanced against the organization's ability to absorb change. Delivering "pace" does not mean reckless speed; it means the optimal speed that maximizes cumulative value without breaking the operational backbone of the company. By designing the tranche structure to accommodate the call centre's capacity, the programme manager ensures that when the change is finally implemented in Tranche 3, it is more likely to be successful and sustainable. This avoids the "value leakage" that occurs when changes are forced upon a business that is not ready to receive them.


NEW QUESTION # 13
Which of the following is NOT set out by the Programme Brief?

  • A. Risks and issues
  • B. Estimated cost
  • C. Analysis of the options available
  • D. Key resources needed

Answer: C

Explanation:
Analysis of the options available is not typically included in the Programme Brief but is developed during the preparation of the Business Case.
The MSP Practitioner clarifies: "Analysis of options starts while preparing business case," meaning the Programme Brief sets out the scope, risks, costs, and key resources but does not contain detailed option appraisal.
This distinction helps ensure the Programme Brief remains a focused and concise document outlining programme intent and governance, while the Business Case undertakes the detailed financial and strategic evaluation required for decision-making.


NEW QUESTION # 14
Which of below sentences best defines programme management?

  • A. Executing dependent projects with aim of realizing benefits
  • B. Action of carrying out coordinated organization, direction and implementation of project dossier and transformation activities to realize benefits of strategic importance
  • C. Coordinating projects under a common umbrella
  • D. Management of set of activities with dependencies and deadlines with aim of realizing benefits

Answer: B

Explanation:
Programme management is defined in MSP as "the action of carrying out coordinated organization, direction and implementation of project dossier and transformation activities to realize benefits of strategic importance." This definition underscores the holistic and strategic nature of programme management, integrating multiple projects and transformational efforts to deliver outcomes that align with organizational strategy.
The MSP Practitioner emphasizes the coordinated nature of programme management that differentiates it from project or portfolio management, focusing on realization of benefits through strategic change delivery.
This definition encapsulates the complexity and scope of programme management, ensuring delivery is both controlled and aligned to strategic goals.


NEW QUESTION # 15
Who approves Business Case?

  • A. SRO
  • B. BCM
  • C. Sponsoring Group
  • D. Programme Manager

Answer: A


NEW QUESTION # 16
In which MSP theme would you expect to find the POTI model?

  • A. Planning and Control
  • B. Leadership and Stakeholder Engagement
  • C. Blueprint Design and Delivery
  • D. Vision

Answer: C

Explanation:
The POTI (Projects, Operations, Teams, and Infrastructure) model is used to define the high-level scope of the Blueprint. The Blueprint theme encompasses the detailed design and delivery aspects of the programme's transformation. As per MSP Practitioner, "POTI defines high level scope of blueprint," situating the model firmly within the Blueprint Design and Delivery governance theme.


NEW QUESTION # 17
Which of the following is not an Input to delivering the capability?

  • A. Blueprint
  • B. Business Case
  • C. Project outputs
  • D. Project dossier

Answer: C

Explanation:
Project outputs are actually the output of delivering the capability, not an input. Inputs to delivering the capability include the Project Dossier, Business Case, and Blueprint, which provide the framework, justification, and detailed design for what is to be delivered.
The MSP Practitioner clarifies: "Project outputs are output of delivering the capability," meaning these are the tangible products or deliverables produced by the projects managed within the programme. In contrast, the Project Dossier contains detailed descriptions and plans for the projects, the Business Case justifies the programme's existence and value, and the Blueprint defines the future state and capabilities required.
This distinction is important because delivering the capability depends on having a clear, approved vision (Blueprint), a solid business justification (Business Case), and a structured project plan (Project Dossier).
Only once these inputs are in place can project outputs be successfully created and integrated to achieve the programme's objectives.
Understanding this flow ensures that programme teams focus on the correct artefacts at each stage-inputs for planning and delivery, outputs for realization and benefits management-ensuring clarity and control throughout the transformational flow.


NEW QUESTION # 18
At which transformational flow basic programme controls are established?

  • A. Managing the tranches
  • B. None of above
  • C. Identifying the programme
  • D. Defining the programme

Answer: C


NEW QUESTION # 19
Which document is created from Programme mandate and works as input for Business Case?

  • A. Programme Brief
  • B. Blueprint
  • C. Programme management plan
  • D. Programme preparation plan

Answer: A


NEW QUESTION # 20
Which of following is output of 'Identifying the programme'?

  • A. Benefit profiles
  • B. Business Case
  • C. Programme Mandate
  • D. Appointment of programme board and SRO

Answer: D

Explanation:
One key output of the 'Identifying the Programme' process is the appointment of the Programme Board and the Senior Responsible Owner (SRO). This formalizes the governance structure needed to provide leadership and oversight for the programme. The MSP Practitioner clearly states: "Programme board is set up by SRO in this process," highlighting that governance is established early to ensure accountability and decision-making capability is in place before the programme progresses further.


NEW QUESTION # 21
Which is not a valid response for a threat?

  • A. Reduce
  • B. Enhance
  • C. Avoid
  • D. Accept

Answer: B

Explanation:
In MSP, threats are negative risks that could impact the programme adversely. Valid responses to threats include Avoiding, Accepting, or Reducing the risk to mitigate potential harm. However, "Enhance" is not a valid response for a threat because it implies increasing the likelihood or impact, which is contrary to risk management objectives.
The MSP Practitioner states: "Threats should be minimized not enhanced," reinforcing the principle that risk responses should focus on reducing negative effects or avoiding risks altogether. Accepting a risk might be chosen when mitigation is impractical or cost-prohibitive but still requires monitoring.
Understanding and applying appropriate risk responses is vital to effective programme risk management and maintaining control over uncertainties that could derail delivery.


NEW QUESTION # 22
The programme is in the 'plan progressive delivery' process. The programme manager has recommended that the funds for the HR Work should come from a different source to the funding for the project work.
During which activity is the SRO responsible for providing formal approval for this recommendation?

  • A. Continue to develop and validate programme plans
  • B. Agree to proceed (or close)
  • C. Confirm business case
  • D. Prepare for the next process

Answer: B

Explanation:
Comprehensive and Detailed 200 to 250 words of Explanation From Exact Extract of project- programme-and-portfolio-management of 5th Edition MSP:
The 'Plan progressive delivery' process is where the detailed plans for the tranches and projects are finalized, and the financial requirements are clarified. This process bridges the gap between the initial design and the start of actual delivery. One of the final and most critical activities in this process (and indeed in most MSP processes) is 'Agree to proceed (or close)'.
In MSP 5th Edition, the Senior Responsible Owner (SRO) holds the ultimate authority to commit the organization to the investment. While the Programme Manager develops the recommendation for funding sources during the planning activities, the SRO must formally approve the entire package of plans, the budget, and the funding strategy before the programme can move into the delivery tranches. Option D is the correct answer because this specific activity represents the "gate" at the end of the planning process. By "agreeing to proceed," the SRO is providing the final authorization for the financial arrangements and the overall delivery strategy. This ensures that the SRO is fully satisfied with the justification and the resource commitments before any significant expenditure begins in Tranche 1. It is a fundamental governance checkpoint that ensures the SRO remains in control of the programme's viability and strategic alignment.


NEW QUESTION # 23
Who is accountable for approval to proceed?

  • A. SRO
  • B. Programme board
  • C. Group of directors
  • D. Sponsoring Group

Answer: A

Explanation:
Although the Sponsoring Group formally gives the approval to proceed, the accountability for this approval rests with the Senior Responsible Owner (SRO). The MSP Practitioner notes: "Approval to proceed is always given by Sponsoring group on recommendation from SRO. SRO is accountable for it." This means the SRO takes responsibility for ensuring the programme is ready to move forward and manages the formal approval process through the Sponsoring Group.


NEW QUESTION # 24
Which of the following is kind of a vision led programme?

  • A. Public programme started to fulfil electoral promises
  • B. Must do programmes due to change in legislation
  • C. Programme focused on bringing organization in tune with laws of the country of operations
  • D. Programme evolved from concurrent, individual projects with need to ensure compliance to organization strategy

Answer: A


NEW QUESTION # 25
Which of the following is an influencer type of stakeholder?

  • A. Supplier
  • B. Business partner
  • C. Media
  • D. Management board

Answer: C

Explanation:
Media is classified as an influencer stakeholder type because it can shape public opinion and stakeholder perceptions, thus affecting programme success indirectly.
The MSP Practitioner notes: "Media can influence other stakeholders as well," highlighting its role in communication and shaping the narrative around the programme.
Understanding and managing influencer stakeholders like media is critical for reputation management, gaining public support, and mitigating risks associated with negative publicity.


NEW QUESTION # 26
In which document would you expect to find the levels of confidentiality to be applied in the programme?

  • A. The Resource Management Strategy
  • B. The Quality Management Strategy
  • C. The Benefits Management Strategy
  • D. The Information Management Strategy

Answer: D

Explanation:
Levels of confidentiality and information security requirements are documented in the Information Management Strategy. This strategy sets out how information will be handled throughout the programme, covering aspects such as access rights, data classification, storage, and dissemination protocols to protect sensitive information.
The MSP Practitioner specifies: "Confidentiality details are defined in Information management strategy," indicating that this document governs the secure management of programme data and communication. It is essential that confidentiality levels are clear to prevent unauthorized access to sensitive information, which could jeopardize the programme's success or breach legal and regulatory obligations.
While Quality Management, Resource Management, and Benefits Management Strategies address different governance aspects such as assurance, resource allocation, and benefit realization, they do not primarily deal with confidentiality.
Information management is critical for stakeholder trust, compliance with legislation (e.g., GDPR), and safeguarding intellectual property or competitive advantage. Clear documentation in the Information Management Strategy ensures that all programme participants understand their responsibilities regarding confidentiality, promoting consistent and secure handling of data.


NEW QUESTION # 27
Which activity from the Smart Meter Programme should be delivered using a continual improvement approach?

  • A. Align the terms and conditions for customer-facing staff
  • B. Switch to installing new water meters gradually
  • C. Develop automatic water leak detection systems
  • D. Develop integrated billing and accounting services

Answer: B

Explanation:
Comprehensive and Detailed 200 to 250 words of Explanation From Exact Extract of project- programme-and-portfolio-management of 5th Edition MSP:
MSP 5th Edition advocates for the use of different delivery life cycles depending on the nature of the work.
While some projects are best suited to a "linear" (waterfall) approach, others benefit from incremental or continual improvement (agile) approaches. Continual improvement is particularly effective when the outcome can be delivered in stages, allowing for feedback and refinement at each step.
Option D is the correct answer because the physical rollout of smart meters is a repetitive process that provides numerous opportunities for learning. By "installing new water meters gradually," the programme can apply lessons learned from the first set of installations to the next, improving efficiency, customer communication, and technical reliability as the rollout progresses. This is the essence of the Plan-Do-Check- Act (PDCA) cycle within the transformational flow.
* Option A (legal/contractual) usually requires a discrete, linear completion.
* Option B (IT systems) often requires complex integration that might be incremental but is less about
"continual improvement" of a repetitive rollout.
* Option C is a R&D/product development activity.
Option D represents the best fit for an iterative, learning-based approach where the pace and quality of delivery are refined based on real-world operational feedback.


NEW QUESTION # 28
Which of the following is an influencer type of stakeholder?

  • A. Supplier
  • B. Business partner
  • C. Media
  • D. Management board

Answer: C


NEW QUESTION # 29
The programme has successfully completed all projects and work according to the delivery plan and is in the
'close the programme' process. All internal staff, who had worked on the programme, must now be transferred back into business as usual roles.
Which role should be responsible for managing these activities?

  • A. Sponsoring group members
  • B. Senior responsible owner
  • C. Business change manager
  • D. Programme manager

Answer: D

Explanation:
Comprehensive and Detailed 200 to 250 words of Explanation From Exact Extract of project- programme-and-portfolio-management of 5th Edition MSP:
The 'Close the programme' process involves the orderly decommissioning of the programme's infrastructure, including its people, assets, and technology. While the SRO is accountable for the closure, the Programme Manager is the role responsible for the practical execution of these activities.
Option C is correct because the Programme Manager's remit includes the "management of the programme team" and the "decommissioning of the programme's organization." Managing the transfer of internal staff back into Business As Usual (BAU) roles is a management task that requires coordination with HR and functional line managers. The Programme Manager must ensure that staff are released in a way that doesn't leave the programme with "resource gaps" during the final administrative wrap-up, while also ensuring the organization reabsorbs its talent effectively. This falls under the Programme Manager's responsibility for the Organization Theme, specifically the aspect of managing the programme's human resources throughout the lifecycle, from the initial "Plan progressive delivery" through to final closure. The BCM (Option D) focuses on the embedding of benefits in the business, not the management of the programme's internal delivery team.


NEW QUESTION # 30
......